Case study · Flow and lead time
Two stick pack lines tripled weekly output and cut leaks by 96% in three months, with the same people and shifts
Health supplement producer · USA · powder stick packs. In short: 30k → 95k units a week; 400 → 14 leak ppm. Client name kept confidential.
30k → 95kunits a week
400 → 14leak ppm
The challenge
Demand was rising, the two lines made 30,000 to 32,000 units a week with a lot of overtime, and 400 sticks per million leaked. The habit was to slow down whenever something went wrong.
What we did
- Involve
- Operators backed every initiative; leaders owned CILT, training and shift handover meetings.
- Engage
- Instead of slowing down, each problem was removed at the root. The vendor reprogrammed the pick-and-place robot, the carton design was fixed with the carton supplier, the filler was upgraded to stop leaks, and set-up time was cut.
- Empower
- Training and CILT so the team kept the lines at full speed.
The results
| Measure | Before | After |
|---|---|---|
| Weekly output, both lines | 30,000–32,000 | 95,000 |
| Leaking sticks | 400 ppm | 14 ppm |
| Overtime | A lot | Sporadic |
| Headcount and shifts | Baseline | Unchanged |
Slowing down felt safe, but it hid every problem. Once the team trusted that problems could be removed, speed became the normal state.
All case studies · The IEE method