Case study · Machine performance

Old liquid line output tripled in five months, building the buffer to install a new line

Nutraceutical manufacturer · USA · liquids. In short: 35k → 110k units a week; 1,000 → 0–1 leaking bottles a week. Client name kept confidential.

35k → 110kunits a week
1,000 → 0–1leaking bottles a week

The challenge

Orders were 40,000 to 50,000 units a week, but the old line made only 30,000 to 35,000. A new line had been bought, but installing it meant eight weeks of downtime, and there was no stock to cover it. Everyone said: don't worry, we're getting a new line.

What we did

Involve
Johan worked on the line and produced alongside the operators to learn what was really going on.
Engage
Eight of nine machines were leveled and aligned. Seven of nine steam-tunnel settings were locked and everyone trained on the other two. Capper set-up was fixed to stop leaks. Bottles that used to be cooled for days and run through the line twice were re-shrunk in a separate steam tunnel instead. Labels were switched from flexo to digital after showing that flexo's real cost, with scrap and rework, was about $0.40 against $0.20.
Empower
CILT (Clean, Inspect, Lubricate, Tighten) with one-point lessons, and weekly hands-on training with the engineers, carried over to the new line.

The results

MeasureBeforeAfter
Weekly output30,000–35,000110,000
Leaking bottlesOver 1,000 a week0–1 a week
Bottles returned for re-labellingAbout 30%0
Real cost per labelAbout $0.40$0.20

The data proved the old line could deliver, but nothing moved until people stopped waiting for the new line and started owning the one they had.