Case study · Quality

Customer complaints cut by 90% and weekly output up 75% in three months, building leadership support along the way

Wellness products manufacturer · USA · capsules and tablets. In short: −90% customer complaints; 80k → 140k units a week. Client name kept confidential.

−90%customer complaints
80k → 140kunits a week

The challenge

The line made 80,000 units a week, and customers complained about cross-threaded caps and wrinkled or misaligned labels. Part of the work was building leadership confidence that results like these were possible.

What we did

Involve
Operators took part in finding the solutions, and shift meetings were started.
Engage
The filler vendor reprogrammed the machine and retrained operators, eliminating empty bottles, and the filler was upgraded. The capper was adjusted, set-ups were cut with better work processes and a second set of product-contact parts, and engineers handled rebuilds and reprogramming.
Empower
Operators were trained to spot defects so bad product never left the plant, backed by CILT and machine training.

The results

MeasureBeforeAfter
Weekly output (stable)80,000140,000
Weekly output (peak)80,000160,000
Customer complaintsBaseline−90%
Empty bottlesOccurringEliminated

The machines were fixed with logic; the lasting change came from helping everyone, leaders included, believe the new level was real.

All case studies · The IEE method

Start with a conversation