Case study · Quality
Customer complaints cut by 90% and weekly output up 75% in three months, building leadership support along the way
Wellness products manufacturer · USA · capsules and tablets. In short: −90% customer complaints; 80k → 140k units a week. Client name kept confidential.
−90%customer complaints
80k → 140kunits a week
The challenge
The line made 80,000 units a week, and customers complained about cross-threaded caps and wrinkled or misaligned labels. Part of the work was building leadership confidence that results like these were possible.
What we did
- Involve
- Operators took part in finding the solutions, and shift meetings were started.
- Engage
- The filler vendor reprogrammed the machine and retrained operators, eliminating empty bottles, and the filler was upgraded. The capper was adjusted, set-ups were cut with better work processes and a second set of product-contact parts, and engineers handled rebuilds and reprogramming.
- Empower
- Operators were trained to spot defects so bad product never left the plant, backed by CILT and machine training.
The results
| Measure | Before | After |
|---|---|---|
| Weekly output (stable) | 80,000 | 140,000 |
| Weekly output (peak) | 80,000 | 160,000 |
| Customer complaints | Baseline | −90% |
| Empty bottles | Occurring | Eliminated |
The machines were fixed with logic; the lasting change came from helping everyone, leaders included, believe the new level was real.