Case study · Flow and lead time
A timed milk run from six test benches to painting cut lead time from three days to one
Swedish hydraulics producer · test and painting. In short: 3 → 1 days, test to delivery. Client name kept confidential.
3 → 1days, test to delivery
The challenge
Tested batches were parked outside painting, and painters spent a long time digging out the right pallet. Storing by delivery day didn't help: Monday overflowed into Tuesday.
What we did
- Involve
- The painters said unloading one pallet took about five minutes, so a delivery every ten minutes would leave them time to spare.
- Engage
- Each of six test benches was picked up every hour, so painting received a pallet every ten minutes, with bus-stop signs, hourly targets at every bench and a red and green light per bench above the painting door. Piloted on one bench, then all six, in about four weeks.
- Empower
- An agency worker ran the milk run for the first week. Then the painting team asked to take it over themselves.
The results
| Measure | Before | After |
|---|---|---|
| Lead time, test to delivery | 2–3 days | About 1 day |
| Pallets waiting outside painting | Many | None |
| Knowing if a line is behind | After the batch | Every hour |
The approach later spread to assembly, where a milk run Johan helped design replaced 11 forklift drivers with 3.
The painters only believed the schedule once they had felt it work for a week; after that, they asked to own it.