Case study · Flow and lead time

A timed milk run from six test benches to painting cut lead time from three days to one

Swedish hydraulics producer · test and painting. In short: 3 → 1 days, test to delivery. Client name kept confidential.

3 → 1days, test to delivery

The challenge

Tested batches were parked outside painting, and painters spent a long time digging out the right pallet. Storing by delivery day didn't help: Monday overflowed into Tuesday.

What we did

Involve
The painters said unloading one pallet took about five minutes, so a delivery every ten minutes would leave them time to spare.
Engage
Each of six test benches was picked up every hour, so painting received a pallet every ten minutes, with bus-stop signs, hourly targets at every bench and a red and green light per bench above the painting door. Piloted on one bench, then all six, in about four weeks.
Empower
An agency worker ran the milk run for the first week. Then the painting team asked to take it over themselves.

The results

MeasureBeforeAfter
Lead time, test to delivery2–3 daysAbout 1 day
Pallets waiting outside paintingManyNone
Knowing if a line is behindAfter the batchEvery hour

The approach later spread to assembly, where a milk run Johan helped design replaced 11 forklift drivers with 3.

The painters only believed the schedule once they had felt it work for a week; after that, they asked to own it.