Case study · Daily management
A tiered daily meeting system, built bottom-up by front-line leaders, lifted output 8–12% and engagement from 60% to 90%
US motion and control manufacturer · Sweden, England and Finland. In short: +8–12% output; 60% → 90% engagement. Client name kept confidential.
+8–12%output
60% → 90%engagement
The challenge
An employee survey showed engagement of about 60%, and the people closest to the work were not part of solving its problems.
What we did
- Involve
- Operators and staff followed the performance of their own areas, logged losses and found root causes.
- Engage
- Front-line leaders built the follow-up in their own areas, bottom up, on boards organized by Safety, Quality, Delivery, Cost, People and Training.
- Empower
- Teams owned their countermeasures and escalated through the tiers, including Capex requests, so problems were answered faster and fixes lasted.
The results
| Measure | Before | After |
|---|---|---|
| Output | Baseline | +8–12% |
| Employee engagement | About 60% | About 90% |
A meeting system only works when people feel the numbers on the board are theirs.