A focused improvement event stopped breakdowns on a bottle line and raised speed by up to 17%

Vitamin and supplement maker · USA · bottling. In short: 2 → 0 breakdowns a shift; +17% line speed. Client name kept confidential.

2 → 0breakdowns a shift
+17%line speed

The challenge

About two breakdowns a shift, 35 minutes each on average, and 13 short stops a shift. Set-up with cleaning took 60 to 65 minutes.

What we did

Engage
The neck bander was repaired and the belts leveled, a cleaning standard was set for the cotton inserter, and the capper and belts were adjusted.
Empower
CILT routines, preventive maintenance, visual standards, set-up organization and daily communication.

The results

MeasureBeforeAfter
Line speed, desiccant products88 bottles a minute103 (+17%)
Line speed, cotton products72 bottles a minute80 (+11%)
BreakdownsAbout 2 a shiftNone after the actions